Wastewater Project:
Village of Suffern, Wastewater Treatment Plant Upgrades
Village of Suffern, Wastewater Treatment Plant Upgrades

In 2019, Delaware Engineering has been assisted the Village of Suffern with planning, permitting, funding, and designing a WWTP upgrade. Prior to Delaware’s involvement, 6 of 8 unit processes were off-line or under-functioning. The plant was struggling to meet interim discharge limits, and the Village was in violation of the compliance schedule specified by a 2011 NYSDEC consent order, citing violations for oxygen demand, ammonia, fecal coliform and total suspended solids. Violations were further scrutinized under the more stringent limits set in the SPEDES Permit in March of 2021.

Within the span of one year, Delaware Engineering organized a regulatory compliance meeting with NYSDEC staff, secured an extension on the Order of Consent compliance schedule, completed a Preliminary Engineering Report, and secured a $2.25 million Water Infrastructure Improvement Act (WIIA) grant to support upgrades to the WWTP and 0% CWSRF financing. 

The $13.4 million upgrade involved new headworks, rehabilitating the trickling filters and primary clarifiers, replacing the secondary clarifiers, switching the mechanical aeration system with a movable bed biological reactor (MBBR), and adding storm and flood resiliency measures. Construction was phased into three contracts, and Delaware prepared the financing applications needed to secure low-cost short-term construction financing from NYSEFC.

Delaware obtained a new SPDES permit for the facility.  The DEC Order was satisfied on schedule even though design and most of the construction was done during the Covid pandemic.

This project protects water in the Ramapo River and benefits identified Potential Environmental Justice Areas and Disadvantaged Communities.

Delaware Engineering provided construction inspection and oversight services along with grant administration for the Village. In 2024 short-term financing closed, converting to long-term leveraged financing.

Facility Capacity: 1.8 MGD

Estimated Costs:  $13.4 million

Grant Funding:
$10.8 million CWSRF
$2.25 million WIIA Grant

More Images of this Project

Grants &
Low-cost Financing

Delaware Engineering, D.P.C. has extensive experience in successfully assisting municipalities in securing hundreds of millions of dollars in low-cost borrowing and grant funds as part of project scope.
Learn more about our Public Infrastructure Grant Writing

Similar Projects…