Delaware Engineering, D.P.C. prepared an Engineering Report and helped secure project funding for a comprehensive upgrade to the Stevensville Water District infrastructure through the New York State Environmental Facilities Corporation (NYSEFC) Drinking Water State Revolving Fund (DWSRF). The Town received a $2M grant and will finance the remainder of the $3.5M project with a low interest loan.
The upgrade project will include the following:
Delaware was retained to assist the Town with implementation of the project, from design and permitting through construction. The project requires regulatory review and approval by NYSDOT, NYSDOH, Sullivan County DPW, and NYSDEC.
Construction of the storage tank was completed in late 2020, and design for the final phases of the project is nearly complete. Construction is expected to be completed in late 2021.