As a result of years of sanitary sewer overflows (SSO) and deficiencies in both its wastewater collection system and treatment plant, the Village of Coxsackie was under an NYSDEC Order-on Consent to solve its SSO issues, including a moratorium on growth in the Village. The Village needed to increase its capacity for both collection and treatment of wastewater in order to remedy its violations and to accommodate new growth.
Delaware completed an engineering study that identified solutions to the sewer overflows. Based on hydraulic modeling and CCTV inspection of the sewer system, the recommendations included relining some sanitary sewers, some storm sewer separation, upgrading sewer pump stations, and up-sizing the main sanitary sewer trunk line. This combination of inflow and infiltration removal, combined with an upgraded WWTP and larger sewer pipe leading to the plant, was designed to deal with the Village’s SSO issues on a comprehensive basis.
The upgrades to the wastewater treatment plant included installing a new mechanical fine screen and a new grit removal system, creating a new Headworks Building, adding a secondary clarifier, and providing other necessary mechanical upgrades.
Delaware successfully secured a $3 million WIIA grant for the Village, along with CWSRF subsidized financing to fund the overall project and solve the sewer overflows. The firm’s scope of work included planning, grant and financing assistance, creation of the engineering study, SEQRA environmental review, plant and systems design, bidding, construction administration, construction observation, and start-up assistance.
In 2021, the Village received a $100,000 EPG grant to conduct further evaluation and investigation of the sanitary collection system with the goal of reducing infiltration and inflows (I&I). Delaware oversaw smoke testing and CCTV inspections within the collection system to identify I&I, and prioritized future potential work to reduce I&I in a Preliminary Engineering Report (PER). The PER has been approved by the NYS DEC, and the project was awarded both BIL and WIIA funding. The Village has closed on short-term financing and Delaware Engineering has begun the design.
Facility Capacity: 1.5 MGD
Project Cost: $17 million
Funding:
- $14.9 million WIIA
- $2.98 million BIL-GS
- $1.59 million CWSRF Financing
More Images of this Project
Village of Coxsakie WWTP
Aerial of Project on the Hudson River
Village of Coxsakie WWTP
Overhead of New Headworks Building Construction
Village of Coxsakie WWTP
New Headworks Building Construction
Village of Coxsakie WWTP
Construction of new Secondary Clarifier
Village of Coxsakie WWTP
Fine Mechanical Screen Installation


